My WES30 Hoisting

WES30 hoisting is a job for experts and needs to be well prepared.

Your local WES dealer will select a local hoisting expert and they will make a hoisting plan for your WES30 wind turbine. If needed a member of the WES project team will be on site to assist during hoisting or hoisting preparation.

Many different questions need to be answered when a hoisting plan is made, the most important ones are:
  • On what kind of soil will the crane operate?
  • Are access road and working platform sufficient or is additional excavation needed?
  • What crane is the best fit for the job?
  • In which weather conditions is hoisting possible?
  • How to offload the turbine from the truck or container?
  • How to move the different components around on site?
  • How to assemble sub components?
  • How to assemble the complete turbine?
  • How many people are needed on site and what kind of equipment is needed?
  • How do the people communicate during hoisting?
  • What safety regulations apply on site?
A WES30 wind turbine with a tubular tower can be erected using only one crane. A WES30 lattice tower can be erected without a crane. Ropes, pulleys, winches, some temporary constructions and manpower allow you to construct the lattice tower without the need for a crane. Once the lattice tower has been erected the nacelle and rotor have to be lifted and connected with a crane. Installing a WES30 on a lattice tower without a crane is also a job that needs to be prepared by your local WES dealer and the local construction team. If needed the WES project team can be involved.

A WES30 wind turbine with a tubular tower is often erected using only one 120 ton crane (or bigger).